For a normal two-car domestic driveway, four to six days on site is typical. The useful thing to understand is where those days actually go, because it explains why a quote promising two days should worry you.
A typical week
Day one — excavation. The existing surface comes up and the ground is dug out to depth, usually 200mm or more for a driveway a car sits on. All of that spoil has to be loaded and carted away. This is the noisiest, most disruptive day and the one where the skip or wagon comes and goes.
Day two — sub-base. Stone goes in and is compacted in layers rather than in one drop, because a compactor only consolidates so far down. This is the part that decides whether the driveway is still flat in ten years, and it cannot be hurried.
Day three — edgings and drainage. Edge restraints bedded and haunched in concrete, any channel drains or soakaways installed, levels and falls set so water goes where it should.
Days four and five — the surface. For block paving: laying, cutting in around the edges, then jointing sand swept in and vibrated down. For resin: the binding layer has to cure fully before any resin goes near it, then the resin is mixed and trowelled out.
Day five or six — finishing. Final compaction, a second sanding where needed, clearing the site and washing the road down.
Resin takes a little longer
Resin-bound needs a solid, cured base beneath it — either concrete or tarmac — and that base must be properly dry before the resin goes on. On a new build-up that adds curing time, which is why a full resin driveway is usually five to seven days rather than four to six.
The exception is laying over a sound existing concrete or tarmac surface. Where the slab underneath is level, sound and draining properly, resin can go straight over it, and that turns the whole job into one or two days. We will dig a test hole and tell you whether yours qualifies.
What causes delays
- Weather — resin cannot be laid wet or onto a damp surface, and no honest contractor will try
- What is found on day one — an old concrete slab, a soakaway, made-up ground or a service nobody knew about
- A dropped kerb — a separate council application that should be approved well before we start
- Access — where a wagon cannot reach, material is shuttled in smaller loads and that adds days
What to plan for
Park elsewhere for the week. Expect noise and a lorry or two in the first couple of days. Keep children and pets off the fresh surface while it cures. And if anyone quotes you a two-day turnaround on a full driveway, ask exactly what depth they are excavating to — the answer is usually the reason.
Want dates for your driveway?
We agree a start date at the quote and tell you honestly what the week looks like, including where your car goes while we are on site.
Common questions
Timing questions
Block paving, yes, almost immediately once the joints are sanded and vibrated in. Resin-bound needs to cure — usually foot traffic after around 12 hours and vehicles after 24 to 48, depending on the temperature. In cold weather it takes longer, and there is no way to hurry it.
Excavation and sub-base work carry on in most weather. Resin cannot be laid in the rain or onto a damp surface, so a wet week genuinely delays a resin job and anyone promising otherwise is going to produce a bad driveway. Block paving is far less weather-dependent, which is one practical reason to choose it if you need a firm date.
Mostly yes, which is worth planning for. The driveway is dug out on day one and is not usable again until the surface goes down. We will talk through where your car goes before we start rather than discovering it on the morning.
Because it is the job. Excavating to depth, carting spoil away, and building the sub-base up in compacted layers is most of the labour on any driveway. The part you can see — the blocks or the resin — usually goes down in a day or two. Any quote where the base sounds quick is a quote worth questioning.
Ready to transform your driveway?
Free quotes, a 5-year workmanship guarantee, and a team that turns up when they say they will.